Projects carried out in thermal energy and industrial automation

More than three decades providing tailor-made solutions in District Heating & Cooling,
automation and energy efficiency.

Energy Exchange and Regulation Package for DHC Substation at Valeo Residence

Scope: Manufacturing, supply and installation of the DHC Districlima substation control and energy exchange package consisting of 2 cold exchangers (500kW) and 2 heat exchangers (350kW).

Location: Barcelona

Engineering: VALLADARES

Client: SURIS

Energy Exchange and Regulation Package for DHC Substations in Offices FR1 and FR2

Scope: Manufacture, supply and installation of a Districlima DHC substation control and energy exchange package in Offices FR1 and FR2.

Offices FR1:
Consisting of two cold exchangers (768kW) and two heat exchangers (387kW).

Offices FR2:
Consisting of two cold exchangers (723kW) and two heat exchangers (431kW).

Location: Barcelona

Engineering: URBANS TBA

Client: DOMINION

Energy Exchange and Regulation Package for DHC Substation at Hotel Tembo

Scope: Manufacturing, supply and installation of the DHC Districlima substation control and energy exchange package consisting of 2 cold exchangers (900kW) and 4 heat exchangers (2x550kW and 2x350kW).

Location: Barcelona

Engineering: –

Client: DOMINION

Energy Exchange and Regulation Package for DHC Substation at Urban 22@ Hotel and Offices

Scope: Manufacturing, supply and installation of Districlima DHC substation control and energy exchange package in Urban 22@ Hotel and Offices.

Hotel: Consisting of 3 cold exchangers (2x310kW and 1x52kW), 2 heat exchangers (263.3kW) and 2 DHW exchangers (150kW)

Offices: Consisting of 4 cold exchangers (2x707kW and 2x357kW), 4 heat exchangers (2×399.3kW and 2×221.1) and 2 DHW exchangers (1x50kW and 1x40kW)

Location: Barcelona

Engineering: IDP

Client: ELECNOR

Shall we discuss your next project?

We would be delighted to study your case and help you with a customised solution.